Microsoft project standard 2013 tutorial free.Project Online Quick Start

Looking for:

One moment, please – Project Server 2013 Quick Start Guides

Click here to Download

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
This can include employee time, equipment time, and even time to see profit. Didn’t match my screen.
 
 

 

Microsoft project standard 2013 tutorial free

 

MS Project will not automatically apply overtime calculations. Click the cell directly below Resource Name heading column to create Resources. Click the Std. Rate field for each resource to costs in hourly default , daily, weekly, monthly and yearly rates. In the following example, the resource Rasmus is left at zero. Click the Ovt. Rate field to enter overtime rates. Double-click the Resource, a Resource Information dialog box opens. Click on Notes tab.

Hovering over it will make the note appear. Set Up Cost Resources You can use a cost resource to represent a financial cost associated with a task in a plan. Examples of cost resources are travel, food, entertainment and training.

So it is obvious that cost resources do no work on a task and do not affect scheduling of a task. Cost value of the cost resource is entered when assigning it to a task. Click the empty cell in the Resource Name column. Type Training and press the Tab Key.

In the Type field, click the down arrow to select Cost. MS Project — Assign Resources to Task MS Project Once the task and resource list are complete, resources need to be assigned to tasks in order to work on them. With MS Project you can track task progress, resource and tasks costs. Click the box below the Resource Name column for the task you need the resource to be assigned. From the dropdown, choose the resource name. In the following screenshot as an example. You can also select multiple resources to work on a single task.

Now click the Assign button. Double-click the Task Name. Click the Resources tab. Click the cell below the Resource Name column. Select the resource from the dropdown list. The window is split in two, Gantt Chart view and Task Form view below it.

In the Task Form view, click under the Resource Name column and select the resource. We can also assign other material resources to the same task. In the Gantt Chart view, you can also look at the project summary task, to note the duration, start and finish dates of the plan. In the following example, Assign Resources is the project summary task identified as Task 0.

MS Project — Track Progress MS Project Once your project plan is ready in MS Project, it becomes essential for a project manager to measure the actuals in terms of work completed, resources used and costs incurred and to revise and change information about tasks and resources due to any changes to the plans.

A Project Manager should not assume that everything is progressing according to plan and should always keep track of each task. Resistance to formal tracking of project management data is normal. You can overcome resistance to tracking by explaining your expectations, explaining the benefits of tracking, and training people to track the task themselves. Save a Baseline To evaluate project performance you need to create a baseline against which you will compare the progress. One needs to save the baseline, once a plan is fully developed.

Of course, due to rolling wave planning or progressive elaboration needed to manage projects one can always add new tasks, resources, constraints and costs to the plan. Also note, it makes sense to save the baseline before entering any actual values such as percentage of task completion. These multiple baselines seem contrary to the definition of baseline. You want to develop separate baseline plans for risk response and recovery.

You will see Baseline Gantt bars displayed together with the current Gantt bars. Update the Baseline for the Entire Project This simply replaces the original baseline values with the currently scheduled values. Update the Baseline for Selected Tasks This does not affect the baseline values for other tasks or resource baseline values in the plan.

Save Multiple Baselines You can save up to 11 baselines in a single plan. The first one is called Baseline, and the rest are Baseline 1 through Baseline It can be used as a project marker. It is visually easy to see how off-track or on-track the project progress is. Because it only specifies dates, it is simple, clear and easy information.

But sometimes this approach might be fine when the actual work and cost values generated are close enough to your baseline schedule. Select the current date.

Check marks will appear in the indicators column for tasks that have been completed. On the right in the Chart portion, progress bars are generated in the Gantt bars of each task. This table includes Work Scheduled work , Actual, and Remaining columns. Click on Task you want to update. For this task, initial scheduled Work was 16 hours, because 24 hours is greater. In the example, a Baseline is saved, because the Baseline does not change and is used as a comparison.

Note: Actual work is rolled up and also reflects on the summary task. Change Start or Finish field in Actual group. You can fill Actual duration field as well. One does not have to finish collecting survey responses before starting the tabulation. Click the box under the Type column and choose the relationship according to your requirement.

Under Lag heading column, enter the lag in terms of hours, days, weeks, or years. You can also apply lag or lead as a percentage. As Soon As Possible means the task starts as soon as the project starts, if there are no dependencies that would delay it. So, no fixed start or end dates are imposed by this constraint type, but of course predecessor and successor dependencies are maintained.

Default constraint when you schedule from the project finish date. Do not enter a Flexible task start or finish date with this constraint. As Soon As Task is scheduled to begin as early as possible. Do not enter a start or finish date with this constraint.

Start No Earlier Task is scheduled to start on or after a specified date. Must Finish On Task is scheduled to finish on a specified date. Click dropdown box for Constraint type. Choose the constraint you would like to apply. It is a better idea to use a Deadline Date which has no effect on the scheduling of a task or summary task. MS Project will alert you with a red exclamation symbol in the indicators column, if the scheduled completion of the task exceeds its deadline date. Enter the cost under the Fixed Cost column for the task of interest.

Enter a Recurring Task Status meetings, status reports, inspection dates can recur with a particular frequency. In MS Project , you can specify recurring tasks without having to assign tasks each time separately. You can also assign resources to these task.

Enter Task Name and choose Recurrence pattern. You can also choose a specific time for the task to start as well. You can add time value in the Start box for Recurring Task Information dialog box to change this. In the following figure, start time of AM is entered. While schedule changes are made, it is also likely that the critical path will change from time to time. One needs to always focus on the Critical Path first, when one wants to apply fast-tracking or crashing to shorten the project duration.

Slack or Float are key to understanding Critical path. All task bars in the critical path, in the Gantt Chart View on the right, will turn Red in color. Gantt Chart View displays some limited resource information, as shown in the following screenshot. It summarizes whether there may be a problem by the red over allocated icon in the indicator column. The Resource Usage view displays resources and all tasks assigned to them underneath the Resource Name.

The left-hand side of the screen lists the Resources and the Task Names together with columns of total information for the resource or assignment. The right-hand side shows a time-phased view. Click on Resource Name column heading. Resolve Resource Over Allocation One would need to either change the scope reduce the amount of work , assign more resources, or accept a longer schedule to resolve overallocation. If you add delay that is less than or equal to the amount of slack on the task, you will not affect the finish date of the project.

Substitute Resources or Add Additional Resources You can manually allot some other resource to the task. You can also right-click on the Time-phased grid in the right hand side window to display amount of overallocation by switching on overallocation. Now you can reduce the assigned hours. In the following example, 8-hour assignment is reduced to 4-hour assignments. You will also notice a new icon in the indicator column to let you know that the assignment work has been edited.

If actual work has been recorded, you must manually reduce the remaining work on the task. Remove Overallocated Resource You can just remove a resource assignment from an overallocated resource. Level Overallocated Resources If resources are overallocated you can use resource-leveling feature in MS Project It works by either splitting tasks or by adding delay to tasks to ensure the resource is not overloaded.

Leveling can delay the individual task finish dates and even the project finish date. Project does not change who is assigned to each task, total work, or assignment unit values.

Project first delays tasks to use up any available slack. Once the slack becomes zero, MS Project makes changes according to priorities, dependency relationships and task constraints such as a Finish No Later Than constraint. You can enter value between 1 and , according to the amount of control you like in the leveling process.

A priority level of will ensure MS Project does not level a particular task. By default, priority is set at or a medium level of control. Tasks that have lower priority are delayed or split before those that have higher priority. Click on the dropdown box and select Priority. Now you can add priority to each task as required. Leveling Steps in the Leveling process are only a few, but it is important to understand what each option does.

Project does leveling and overallocated indicators are removed If leveling is done completely, sometimes this might not happen. In Resource Leveling dialog box, under Level calculations, try to use Manual more often. For examples, if a resource is overallocated, for say half an hour more in a week, from 40 hours to Doing so will not level resources, but it will determine when Project displays overallocation indicators next to resource names.

In Resource Leveling dialog box, under Level calculations, use the clear leveling values before leveling checkbox is selected. Doing so will ensure Project removes any existing leveling delays from all tasks and assignments before leveling. Here you choose to level either the entire plan or only assignments that fall within a date range you specify.

Numerically higher ID numbers for example, 10 will be delayed before numerically lower ID numbers. You might want to use this option when your plan has no task relationships or constraints. In Resource Leveling dialog box, under Resolving overallocations, you have several options that you can select. MS Project will use only the free slack within the existing schedule, which could mean that resource overallocations might not be fully resolved.

Selecting this checkbox allows Project to add a leveling delay or split work on assignments if Leveling Can Create Splits in Remaining Work is also selected independently of any other resources assigned to the same task. This might cause resources to start and finish work on a task at different times. Center for Marketing and Consumer Insights. Center for Supply Chain Management. Meet Dr. Ryann Reynolds-McIlnay, assistant professor of marketing and merchandising management.

Our centers and initiatives give you hands-on, experiential learning opportunities. Interested in market research? Want to advance gender equity and inclusion? We’ve got that, too. More than 3, students 30k Alumni worldwide 28 degrees and areas of focus. Degree programs and focus areas developed with industry advisory boards representative of more than area and national businesses. We’re graduating the workforce that you need. At the College of Business, we’re inspired by everything around us.

We support bold risks, big dreams and never giving up. We prepare you for a diverse world and teach you to become engaged citizens and business leaders. Are you ready to get started? Transform your life with our online and in-person programs taught by College of Business faculty and industry experts. Discover Classes. There are more than 30, College of Business alums in the world. Each year, hundreds of you inspire and mentor current students, and support internship and job opportunities at your companies.

Because of you, the Beaver family is strong. These tutorials were developed and funded by the College of Business at Oregon State University for use in our project management courses. They may not be used without permission by other colleges, universities, organizations, institutions or individuals. Please contact Dr. Pauline Schilpzand Pauline. What you see when you open MS Project How to create a WBS. Manual Scheduling vs Auto Scheduling. How to Enter Estimated Duration.

How to enter predecessor information to create a project schedule. How to change a timescale. Formatting a Gantt chart. Network Sensitivity. The difference between free slack and total slack. How to introduce lags into a schedule. How to display the schedule as a network. How to Create a Resource Pool. How to Assign Resources to Specific Tasks. How to Designate a Start Date for a Project. How to Insert Milestones into Your Schedule. Make certain that your first task is a summary task under which all other tasks are subordinated.

You can also include major function, output, and input columns within the entry table simply by clicking on Insert and then Column and typing in the name of the column, followed by clicking on OK. To show that a particular task can begin only when the predecessor task has completed, the two tasks must be linked.

After you decide the task sequence, you can link the tasks, as follows. In the cree name field, select two or more tasks that you want to link. To avoid confusion, it is best to select only a pair of tasks at a time.

The first task you click on will be assumed to be the precedent task and the second task that you click on will be assumed to be the subsequent task. Click vree Link task button on the tool bar. It is microspft button with the solid chain link icon.

MS Project generally links tasks as Finish-to-Start tasks, i. In the task name field, double click the task you want to link. The task information dialog box appears. Click the predecessor tab. Click in the Type box and then click the drop down arrow to see the four types of dependency relationships that can be established.

You can also select link under the Edit menu item on the menu bar after selecting the pair of tasks to be linked. In these latter cases, the analyst wants projwct to start together or finish together.

To change the link type, identify the starting task by clicking on it. Select the predecessors tab and click on the link type field. To do so, begin in the Gantt View with the Entry table visible. Slide the partition to the right to expose as much of the entry table as possible.

You should see two side-by-side columns the start column ;df the finish column. By pddf any of the dates in these columns, you are setting a hard date constraint. If you do so, a flag will appear in microsooft very first column how to use microsoft project pdf free the entry table, the odf labeled I for information. If you rest the cursor on that flag, a message appears how to use microsoft project pdf free informs you of the hard date constraint that has been applied to the task.

How to use microsoft project pdf free one hard date constraint can be set per task at the start date or at the stop date, but not both. Resources can be places, departments, businesses, people, equipment–anything required hw complete an activity. When you create an hos, you assign a resource to a task. The resource issue makes the project. You can assign: Individual resources Assign resources part time Several resources Remove resources from a task Replace one resource with another.

In the Task name field, select the task to which you have to assign a resource. Post a Comment.

 
 

Quick Start Guides for Project Online and Project Server .Project – Beginner Course | Training Courses | Software | replace.me LMS

 
 

Project Online More Need more help? Expand your skills. Get new features first. Was this information helpful? Yes No.

Thank you! Any more feedback? The more you tell us the more we can help. Can you help us improve? Resolved my issue. Clear instructions. Easy to follow. No jargon. Advanced SystemCare Free. WinRAR bit. VLC Media Player. MacX YouTube Downloader. Microsoft Office YTD Video Downloader. Adobe Photoshop CC. VirtualDJ Avast Free Security.

WhatsApp Messenger. Talking Tom Cat. Clash of Clans. Subway Surfers. TubeMate 3. Then tab over to the Finish row and enter an end date. Microsoft will automatically enter the amount of time it will take to complete the task in the Duration row. Add Tasks to the Timeline To add tasks to the Timeline, click the View tab and click the Timeline bar that appears above the task list.

Then right-click on a Task cell and choose Add to Timeline from the list and click it to add the task to the timeline. Tip: You can select all tasks in the list and then right-click on the mouse and select Add to Timeline to add all the tasks simultaneously.

Set up resources in Microsoft Project through the Resource tab in your project. Use this tab to establish the people, or resources, that will be assigned to tasks on your timeline. The Resource Sheet will appear on the screen. Once your resources are added to the project, you can easily view who is available to take on the task based on their workload, and manage how much time each team member will spend on tasks in the Resource Management view.

Once you have created a timeline and set up your resources in Microsoft Project, use the Gantt chart view to assign tasks. One benefit of MS Project is that it can calculate the time it will take a person to complete a task based on their availability. If an important part of the project needs to be done quickly, you can assign multiple people and the program will estimate the time needed to complete the task accordingly.

This also alerts the people assigned to the project to the time that is required of them. Click the Gantt chart icon in top left corner of the window.

Open the Task Form You should still be in the View tab. Click the Details box in the ribbon. The Task Form should appear on the lower half of the screen. Click the box under Resource Name and choose a resource from the drop-down menu. Then click OK. You can add another person to the same task by clicking the area under Resource Name and choosing the name you want. Click OK. As you assign tasks, the amount of time will be added to the Gantt chart.

Note: Clicking the Next button located on the right side of the OK button will load the next task in the Gantt chart. When scheduling tasks with Microsoft Project, you have two options. You can assign and track tasks manually, or use the automatic feature to schedule tasks based on dependencies, calendars, and constraints. Learn how to use the automatic feature below: 1. Click Edit project settings. The default is set to Manually Scheduled. Select and click Auto Scheduled and click the OK button.

To create task dependencies in Microsoft Projects, link any two tasks in Gantt chart view. When linked, all changes made to the first task affect the second. Select Tasks to Link Click the Task tab in the menu bar. Identify the two tasks in the list that you want to link.